Your ad can replace the one shown here from just £8.99 / month. – Click here for more info.
The Essential Guide » Initial Stages of a Project » What Time of Year is Best to Self Build / Renovate / Convert / Extend?
What time of year is best to Self Build or Renovate?
This is “One of those questions”! – One that all Self Builders and Renovators often have strong preconceptions about, and are keen to get a "sensible" answer to, - before they get too far into the process of planning their projects.
The problem is that when I give the honest answer, and say: “Any time of year is fine”, people tend to look at me as if to say, “Well that shows how much YOU know!”
-----------------------------
Why do I give that answer?I have worked for many years as a “Site Engineer”, “Commercial Site Manager” / “Building Consultant” and “Housing Developer”. I have also completed my own “Self Build projects.
1) Time of year and Self Build:
Having worked in all seasons and in all types of weather, and temperatures, I would have to say that:
“In my opinion, the time of year does not need to have any major effect on any of the site activities involved in a Self Build project, - and that in fact, some of the times of year that people would imagine are the worst times to start, can actually be the best!”
However, what can have a dramatic effect on progress, and can cause the contracts to go both over time and over budget is the “day to day” weather.
You may come back immediately, saying: “Well don’t be daft. - The time of year will surely dictate how the weather is”. - That is not actually the case. – You need to remember that we live in the UK!
I have worked through whole winters where we have not really lost a day due to bad weather conditions, and through summers which have been a complete wash out, where we have lost “weeks on end” of progress.
Example 1: Groundworks:
If there is one area of the job which will be affected by the “time of year” you would think it would be Groundworks. In fact that is true, but maybe not in the way you may think:
If I am starting a new project, and I am programming the Site Clearance / Foundations and Drainage work for the “real winter months” of December / January / February, I will often make faster and better progress than if I am starting the work in spring, autumn, or sometimes even the summer.
For a start the “vegetation” across the site will normally have “died down” from what it was in the summer, so there is often not as much “Site Clearance” to do, and therefore not as much “waste” to get rid of, either by skip to a tip or by burning it on site (where allowed).
If I dig a footing (foundation trench) in a period of very cold weather, I tend to find that the sides of the trench stand up far better, and very rarely “cave in” whilst we complete the excavation works and wait for the concrete. The reason for this is “ice”!
In Spring, Summer or Autumn, if your are excavating trenches on a plot with a high “water table”, or if it has been raining heavily just before you start to excavate, either the ground can become “sodden” to quite a depth, or there can be many pools of lying water in the “dig area”.
As soon as you start to excavate, this water will start to pour down the sides of the newly dug trench, quickly turning “soil” into “mud”. - Then, - if there are stones or rocks in the sides of the trench, what often happens is that these get washed out, and the sides of the trench start to collapse, covering the bottom of the excavation with mud, stone and rocks. - It can create a real mess! All of the mud and debris will then have to be removed (often by hand), before any concreting can start.
When that happens, not only does the extra work of emptying and “making good” the trench cost you time and money, but you could also end up paying hundreds of pounds extra for concrete to fill in all the “voids” that the collapsing banks have left you with!
If you are in the middle of a “cold snap” in February, there you are le4ss likely to have had rain, and there is at least a chance that the ground and any “lying water” will be frozen, and therefore water possibly won’t cause you ANY problems whilst you excavate.
So, my time of year “of choice” in the UK for excavating trenches would always be WINTER!
So: - What about the temperatures in winter? – Surely you can’t lay concrete when it’s icy?
“Concrete setting” (or “going off”) is caused by a chemical reaction between its “constituent parts”.
As this reaction takes place it creates heat. – Concrete, whilst it is “going off” has qualities similar to a radiator! –A bit of ice or even rain isn’t going to hurt it! – Within a few hours of it being poured, any new rain will sit harmlessly on the surface.
Conclusion: Taking the two parts of the equation together it can actually make perfectly good sense think about starting the ground works in winter.
Example 2: Brickwork
Laying bricks and blocks is a part of the building process which can start within a few days of moving onto site, and continue through to pretty much the completion of the whole project.
You start with brickwork underground up to dpc (damp proof course), then whether you are building in Timber frame or Traditional, you will usually still need to build at least one skin in brickwork or blockwork.
There may be internal walls to either “build new” or “make good”, - and there could also be drainage, garden walls etc.

Because the sections of the project which require bricklaying of one type or another are spread throughout the project, long periods of rainy weather could really put a spanner in the works.
If bricks are wet, they are harder to lay and can give you a messy finish. If it rains soon after you have laid bricks, water can start to run down the face of the brick and wash out the mortar. Mortar on the “spot board” can also get watered down (and any “colour dye” could be washed out of it). Bricks can get splashed with mud as vehicles pass close by, often resulting in some of them being thrown away and wasted.
Unfortunately in this country we can’t guarantee that ANY time of the year will be “rain free”. In fact the least likely time for rain over the past few years (in my experience) has seemed to be the winter! – Spring is usually fairly wet, summers have often been a washout, and autumn also fairly wet.
So, we all basically have to accept that. Although some areas of the country are “drier” than others, the weather is not going to be something we can “plan around” by building at one time of the year or another.
Instead, whenever we decide to start work on the parts of the project such as the brickwork which are going to be affected by weather conditions, we simply need to think about ways to plan ahead to minimize the disruption that can be caused.
If you read more of this guide you will pick up hints and ways to try to maximise the rate of progress of all sections of the project. – The faster your get to the point of being “watertight”, the less effect the weather will have on the project overall. – That in itself is one way to beat the weather, up to a point.
However, you need to try to keep progress going on sections such as brickwork, whatever the weather, you may want to consider “weather protection” methods, such as covering the whole of the scaffolding with tarpaulins to keep of the rain.
Conclusion: There is no real “best time” to start brickwork. – Being well organised and getting rapid progress when it IS dry, plus possibly weatherproofing the working area are the best ways to beat the bad weather.
Example 3: Timber Frame
When your timber Frame comes to site, it will have significant levels of moisture in it. The panels are often stored outside once they have been fabricated, so at least the ones that were “at the top of the stack” could be soaking wet. All the timber used in the frame should have been “treated” with preservative, so rain should not do it any harm.
The “vapour barrier” (usually the green or blue covering that you see on the face of timber frame panels) is not damaged by rain, and all the fixings that hold the frame together should be rust resistant.
So, the frame itself should not cause you any problems “due to rain” at any time of year. Even if it’s icy while it is being erected, once the frame is up and the brick or blockwork starts to be built, the ice will melt, and the frame will start to dry out in just the same way (although slower) than it will do during the summer.
What DOES happen with timber however, is that, as it absorbs moisture, it expands slightly.
So, if your panels are literally “sopping wet” there is a chance that once they dry out they will then shrink slightly. You won’t generally notice this until after you have moved in and start to use the central heating.
What can start to happen then is, as all the individual parts of the frame start to dry out and shrink, you start to see cracks appearing at joints (normally at the tops of walls where they meet the ceiling). Once all the drying out process has finished you will need to fill these cracks and make good the decoration. – This is a cosmetic exercise and is not a major problem (“Traditionally” built houses, if anything have more problems with shrinkage than timber frame).
Where the weather WILL have an effect on a project using a Timber Frameis where the“Erectiongang” are not physically able to work because the weather is causing “dangerous” conditions. Rain can stop them working altogether, especially if they are working at “height” and the timber has become slippery. The same goes for icy conditions.
However, apart from the occasional very bad “cold snap”, ice usually melts during the day by about 10am, so progress (if not “full progress”) can normally be made most days, and due to the fact that the frames go up so quickly, any delays on the erection of a timber frame due to Any bad weather conditions, are normally fairly minimal.
Conclusion: Overall, there are not really any times of year that you would say “We can’t think about starting to build
the timber frame”.
Example 4: Other activities
Most of the rest of the building activities will be affected by the weather to a certain extent, but for most, if not all of them, the time of year will not be a critical factor affecting “speed of progress”.
Believe it or not, there are some activities which are held up if it’s too sunny! Concrete can dry out too quickly in bright direct sunlight, which can cause “cracking and crazing” on the surface. If there is reinforcement in the concrete (which there often is), water can then in some cases get through to it through these cracks and start to rust it. – So the sun is JUST as capable of causing you delays to your project as is the rain!
If you want to maintain a good rate of progress, one thing to keep in mind FROM DAY ONE (especially on a Self Build project), is to plan to “get the roof on” as quickly as possible.
Even if the roof is only “felt and battened” (i.e. not tiled), you open up a whole new area of the project that you can start work on.
In this respect Timber Frames have the advantage over Traditional building, because, once the floor slab has been poured, the Timber Frame can be erected in sometimes less than a week. - If you can then line up the roofers to quickly complete at least the felt and battening (which doesn’t usually take long), you can be at least partly “oblivious” to the effects of the weather. Then, even if the bricklaying is held up for 2 or 3 weeks, as long as you can be working inside, you need not lose any significant amount of progress over all.
Conclusion: For most building activities there are no real “no go” times of year. – Timber Frames have advantages over Traditional Build when it comes to being affected by weather conditions, but forward planning is important whichever time of year or whichever build method you adopt.
Example 5: Busy periods in the industry:
Summer does tend to be the busiest time in the building industry. “Clients” don’t tend to want to start work when it’s cold and wet. So, whether or not the summer is a washout, Contractors and Sub Contractorswill tend to have a higher workload during the late spring, summer and early autumn months. Then there is the fact that in the summer, most people, at some stage want a holiday. - this can "take out" a significant proportion of the "available workforce" for about 7 weeks a year!In theory, this could cause you problems trying to get good quality trades people in at those times of year. However, in fact the effects of this extra workload are fairly minimal. – During busy periods you may need to “book” the people you need a bit earlier if you know you will want them on a certain date.
Sometimes during busy times of year, due to bad weather or other circumstances other projects your chosen “sub contractors” are working on, run over time, - they may be delayed by a few days on getting to you. – These delays can then have “knock on” effects on your project (by you having to put the next trade off and possibly then losing them for a few weeks to other work).
Conclusion: Summer is generally a busier time of year than winter, so you may find it a little harder to find good quality contractors who are available when you need them. - The trick, as usual is to “do your research and plan ahead”. In other words, choose the best people for the job EARLY ON, by doing some research, tendering, and meeting up with the various Contractors and Sub Contractors. Tell them about the “timescale” plans for your project, and then keep in constant touch with them to let them know how things are looking “week to week” so they can plan their other work “around” coming to your project. - If you do this then you should not have too many problems.
Over All Conclusions:
As I alluded to at the top of the page, there is really no “bad time” to start work on one of these projects.
One of the problems we face as builders in this country is that: “You can only ever be sure of the weather when you look back at it”! - We don’t get “sensible weather” like they do in some other countries where you know every day what tomorrow is going to be like – (It’s going to be like today!).
We have to think on our feet, and take each day as it comes. So really, it makes no difference whether you decide to pour the concrete in January or June, April or August, you stand just as much chance of “hitting good weather” as you do of “hitting bad”. – It’s purely the luck of the drawer!
You can take precautions to try to safeguard against losing time and incurring extra costs due to bad weather. You can cover the scaffolding, you can use “trench shoring” to stop the sides of your trenches caving in, you can wait until you get a good weather forecast before you start work on the footings, but for every problem you may think you solve by doing that sort of thing, you can bring in another “just as real” problem.
My thoughts and experience in building new works or renovating bring me to a point where I would give the following advice:
1) You will NEVER guarantee the weather, no matter what time of year it is. You will NEVER guarantee the temperature. You will NEVER guarantee that you can get the right people at the right time. - So why put your project back month after month, waiting for something that might never happen?
2) Plan for problems from the outset, watch out for them coming, and deal with them as they arise.
3) Make sure you leave enough in your budget to take care of any extra costs which occur due to seasonal or weather factors.
And, whatever the time of year, don’t wait for the weather. - Just get on with it!
.jpg)
« return to guide contents
Your ad can replace the one shown here from just £8.99 / month. – Click here for more info.



